How long does it take for my plans to be reviewed?

Category: Status of Permit

Permit Techs will be placing due date on the plans based on the following max. timelines (working days):

- 7 days for Corrections

- 7 days for Revisions

 -10 days for Expedited Permits (any disaster)

- 10 days for Express Permits, including Solar (Hot water and PV’s)

- 15 days for new SFD; T.I.’s and Large Garages

- 30 days Large Custom Homes & Large Commercial